  1. The new drilling company for this year’s drilling campaign is called Priority Drilling, they are experts in deeper drilling as we are doing at the moment
  2. Priority have recruited two local lads, one of whom was used last year by the contractor last year, Energold. One of the local lads used by Energold last year has been working overseas for them in Africa and Europe
  3. Drilling is only carried out by day. The first hole is nearly complete. A second drill rig has arrived on site and commenced drilling last week so that the work can be carried out quickly
  4. We have added sound reducing blankets around the rigs as well as bales, this has been successful so far in minimising noise levels.
  5. Any issues contact Jeff Harrison mob: 07403568770

Related Articles:

Cornwall Resources Ltd – Exploration Drilling Planning Application

Cornwall Resources Ltd – Exploration Drilling Planning Application

Location: Callington Town Hall The Town Hall, New Road, Callington, PL17 7BD Dates: Wednesday 18th January 1:00 pm – 3.30 pm Friday 20th January 5.30 pm – 7.30 pm Saturday 21st January 10:00 am – 12:00 pm Cornwall Resources Limited (CRL) is the operating company for...

Mining Update October 2022

Mining Update October 2022

Excerpt from the Western Morning News Thursday 29th September 2022 'As the Cornish Mining Conference takes place in Falmouth this week, demand for secure supplies of  metals and minerals in an increasingly volatile world presents a huge opportunity for Cornwall and...

Cornwall Resources Ltd Community Update Event

Cornwall Resources Ltd Community Update Event

Location: Callington Town Hall Town Hall, New Road, Callington, PL17 7BD Dates: Wednesday 12thOctober at 5:30pm - 8pm Thursday 13thOctober at 2:30pm - 5:30pm Friday 14thOctober at 4pm- 7pm. Cornwall Resources Limited (CRL) is the operating company for the Redmoor...